From auditing many construction investment projects, ATAX has found that the proposed finalisation value is often reduced because of recurring errors. Identifying these errors early helps investors and project management units complete their dossiers and shorten the verification and approval of finalisation.
Accepted and paid quantities exceed actual quantities or as-built drawings; one item is counted in several work items. Prevention: strictly reconcile accepted quantities with as-built drawings and construction logs.
Unit prices applied at the wrong time, norms unsuitable for construction conditions, incorrect adjustment coefficients. Prevention: check estimates and price adjustment bases against contract terms.
Lump-sum contracts with payments for variations that are not eligible for adjustment; adjustable unit-price contracts without correctly applying the formula. Prevention: follow contract conditions closely during acceptance and payment.
Additional quantities paid before contract appendices or adjustment approvals are in place. Prevention: complete approval procedures for variations before payment.
Missing decisions approving project or estimate adjustments, contractor selection results or completion acceptance records. Prevention: build a checklist of legal documents from commencement and update it regularly.
Recurring operating expenses or costs of other projects wrongly recorded as investment costs. Prevention: keep separate ledgers for each project and work item.
Missing approved plans, payment records or receipts from compensated persons. Prevention: keep complete payment files for each household.
Overdue contract advances not recovered; balances with contractors not matching. Prevention: reconcile balances periodically and before preparing the finalisation report.
Unreasonable allocation of common costs (project management, consultancy, interest during construction) to each asset, affecting historical cost and depreciation. Prevention: set clear and consistent allocation criteria.
Finalisation later than the prescribed deadline leads to lost records, dissolved contractors, difficult reconciliation and possible disciplinary liability. Prevention: plan finalisation as soon as completion acceptance occurs and appoint the auditor early.
An independent audit is not only a mandatory procedure for many projects but also a tool that helps investors control costs and reduce the risk of disallowed costs. Learn more about the process: Construction project audit and its process (in Vietnamese).